The project involved the installation of 57nr load bearing piles into clay, with a maximum depth of 22.1m—well within the capabilities of our SR30 piling rig. The 300mm diameter piles were constructed to serve as the foundations for a new apartment block, ensuring stability and structural integrity
After consulting with our client, it was agreed that CFA load-bearing piles would be used to provide the foundations for the new apartment block. The pile mat footprint easily accommodated the piling rig, enabling high production outputs on-site. Reinforcement cages, each 6m in length, were installed using an attendant excavator, allowing the piling rig to remain productive throughout the process.
The project was completed on schedule, ensuring a smooth handover with the client